Will Illinois Homeowners Pay for Data Center Wires? What the Attorney General and ICC Say About ComEd's Large-Load Deals
Will Illinois Homeowners Pay for Data Center Wires?
What the Attorney General and ICC Say About ComEd's Large-Load Deals
When a data center connects to the grid, someone pays for the new lines and equipment. The question in Illinois is whether that someone is the data center or the neighbors down the street.
The Attorney General's warning
In January 2026, the Illinois Attorney General's office protested two ComEd transmission service agreements with data center developers at the Federal Energy Regulatory Commission. The AG said the payment safeguards "do not prevent existing customers from paying the costs caused by this large, discrete load." The AG warned that costs could flow into transmission prices through formula rates. ComEd said the agreements include a ramp schedule, credit obligations, shortfall payments and a published termination-fee schedule (ComEd's position).
What the ICC decided
In March 2026, the Illinois Commerce Commission approved, with modifications, ComEd's changes for serving large customers, including minimum payment requirements and financial security if a data center uses less power than estimated. Deposits now start at $1 million for projects requesting 50 to 200 MW and rise by $500,000 for each additional 100 MW. The tariff does not apply to data centers already on the grid.
Advocates say it is not enough yet
Brad Klein of the Environmental Law and Policy Center said the order protects only the portion of costs assigned to data centers. He estimated that infrastructure for a single data center could cost $50 million or more. The Union of Concerned Scientists says ComEd ratepayers already carry hundreds of millions of dollars in costs to connect data centers. The ICC opened a follow-up proceeding, to be completed within eight months, to consider added protections.
What this means for your household
Until the follow-up work is finished, some of the cost risk may still sit with all customers. You cannot control that process, but you can control how much of your own electricity you buy. Solar produces power at your home, and a battery can store it for the evening.
How third-party ownership (TPO) works
In a TPO program, a company installs, owns and maintains the solar and battery system at your home. You pay for the power it produces without buying, leasing, or financing equipment. Many programs are designed to come in below utility rates, with savings of up to 40% depending on your home and program.
Here is what a TPO solar and battery program can offer:
Home-produced power that reduces what you buy from the grid
Stored solar for peak evening hours
Backup power during outages
Savings and eligibility depend on your home, utility and program.
To find out if your home qualifies for a TPO solar and battery program, visit myhomesolution.org
Additional resources
Utility Dive, Illinois AG files objections to ComEd data center agreements at FERC: https://www.utilitydive.com/news/illinois-ag-files-objections-to-comed-data-center-agreements-at-ferc/809576/
Environmental Law and Policy Center, ICC orders investigation into data center risks in ComEd case: https://elpc.org/news/icc-orders-investigation-into-data-center-risks-in-comed-case/
Capitol News Illinois via NPR Illinois, regulators OK ComEd's plan to increase deposit costs: https://www.nprillinois.org/illinois/2026-03-20/regulators-ok-comeds-plan-to-increase-deposit-costs-for-large-load-projects-like-data-centers